Why do we measure?
Metrics are often thought of as the electric third rail of organizations. If not evil, they are considered highly hazardous and something every team member wants to avoid.
We measure things, so we have data to ask the right questions. For a team, those questions are “How can we be more effective?” and “How can we improve our quality?”
We measure things so that we can improve, grow, and learn how to repeat success.
What do we measure?
Which brings us to the next question, “What do we measure?” There are a wealth of metrics available for teams to use or have used on them. Unfortunately, there are more useless metrics than useful. Eric Ries, author of Lean Startup, calls them “vanity metrics” because they look good — and make you feel good — while offering little in the way of actionable value.
When boiled down, there are six key levers that organizations care about and use to track success. Successful organizations have healthy ways to measure all six of these measures.
- Value: Are we meeting the customer’s needs?
- Predictability: Are we able to deliver what we planned?
- Productivity: Are we getting more done in the same amount of time or with the same resources?
- Quality: Is the product free of defects and issues?
- Sustainability: Can the organization maintain this pace indefinitely?
- Growth: Is the organization growing and learning?
With the goal of “helping the team to improve their effectiveness and improve their quality” and the caveat “your mileage may vary,” below are my four go-to metrics for an agile team to gauge their ability to impact the organizational success levers.
How do we measure teams?
There is no silver bullet for measuring team success. Counting only one metric makes it easy to get tunnel vision. Be it the team focusing on just making the metric better (often through gaming the system) or management using the metric to drive all decisions, you can end up with a product or organization that looks good while secretly, or not so secretly, driving off a cliff.
While one is bad, don’t fall into the trap of too many. If you are using ten metrics it is more likely that different parts of the organization will focus on different metrics, driving a wedge into the efforts to align the organization. Humans are best able to handle three to five things at a time.
4 Metrics to Improve Agile Team Performance
Based on experience, I have found there are three lagging and one leading measure that support one another for good team health and growth:
- Cycle Time (Productivity)
- Escaped Defect Rate (Quality)
- Planned-to-Done Ratio (Predictability)
- Happiness Metric (Stability)
Let’s examine each of these in turn and see how they can help a team to be more effective, have higher quality, and be able to maintain a constant pace indefinitely.
Cycle Time (Productivity)
Cycle time is your direct connection to throughput and is a way to measure team productivity, which itself connects to effectiveness. The shorter the cycle time, the more things are getting done in a given timebox. This concept is demonstrated in this short video on Batch Flow. As you can see, the bottom flow has a cycle time of twenty-nine seconds to deliver ten units of value. The top flow has a cycle time of one minute to deliver the same amount of value. For every minute, the bottom flow can deliver twice the value as the top flow.
Cycle time can be most simply measured from when work starts to when the work is done. In software terms, I tend to think of this as “hands-on keyboard” time. Measuring cycle time is best done automatically via your agile lifecycle tool of choice, though measuring with a physical task board will also give you useful data.
Escaped Defect Rate (Quality)
This measure tracks overall quality and is the connection between customer satisfaction and the team. The lower the defect rate, the more satisfied the customer is likely to be with the product. With a high escaped defect rate, even a best-in-class product is going to have a lot of unsatisfied customers. Think of the iPhone “antenna gate,” or the Toyota airbag fiasco.
Escaped defects are measured by the number of problems (bugs, defects, etc.) found in the product once it has been delivered to the user. Keep in mind, though, that until a “story” is done, it is still in process, so any issue identified while work is being done is not a defect, it’s just another task to complete before the work can be considered “Done.”
Planned-to-Done Ratio (Predictability)
This metric is a way to measure predictability, which also impacts effectiveness. If a team commits to thirty product backlog items and only delivers nine, there is about a 30 percent chance of any one item being delivered in the Sprint. If, on the other hand, the team commits to ten PBI and delivers nine, there is roughly a 90 percent chance of any individual PBI being completed. This predictability helps both the Development Team and the Product Owner.
Measuring the Planned-to-Done ratio is a simple exercise of documenting how much work the team commits to doing at the start of the Sprint versus how much they have completed at the end of the Sprint. Be careful with teams that have challenges with adding work in the middle of the Sprint. If this is common, you will want to pay careful attention to what “Done” work was part of the plan vs. added later. If a team planned to do ten items, added five items and only got the five added items done, then their Planned-to-Done is 0%, not 50%. They did not complete any of the planned work.
For teams using Scrum or any kind of short-term goal setting, I also recommend tracking planned to done on Sprint Goal. The Sprint Goal is a problem to be solved for the user, a cohesive collection of value. You can deliver a dozen Product Backlog Items in a Sprint and not deliver on your Sprint Goa cohesive value.
Happiness Metric (Stability)
This is the team “health” metric. It creates awareness that puts the other three metrics into a better context. If all the other metrics are perfect and happiness is low, then the team is probably getting burned out, and fast. Organizations can no longer afford to be unsustainable. When the cost to replace even an entry-level employee can be 50% of their annual income, we need to focus on the health and engagement of the team.
The Happiness Metric is also the only leading indicator in this set of metrics. It serves as an early warning system to help teams and the leaders that support them head off challenges with the other metrics.
For measuring happiness, build it into your Sprint retrospectives. Open every retrospective with the team writing down their happiness scores on whatever scale you choose. Track these numbers from sprint to sprint to see the trends. One ScrumMaster I worked with created a simple Google Survey and sent this out before the Retrospective. This allowed him to add in the supporting questions of the full Crisp Happiness Metric, as detailed in this Scrum Inc. blog post.
How These Four Metrics Work Together
Cycle Time and Escaped Defect Rate are highly quantifiable and well-understood across industries. Smaller numbers mean you are delivering a higher quality product, faster. Planned-to-Done has an immediate and real impact, and provides an “early win.” Over time, it becomes useful in mapping predictability, which helps in forecasting. The Happiness Metric is the “human factor,” which lets us gauge the overall team health.
The first three measures form a self-supporting triangle that prevents gaming the system. If you crash your Cycle Time, then defects will almost certainly go up. A high Planned-to-Done ratio can be great, unless cycle time is through the roof, showing the team is getting very little done per Sprint. Finally, by layering the Happiness Metric over the rest, you can see the human side of the equation. A low happiness score is nearly always a sign of underlying problems and can be a leading indicator of something else.
What About Value and Growth?
Value is far more subjective and personal to an organization. This can be a Net Promoter score, revenue, average active users, etc. Important tips to remember are that value comes in two flavors: Tangible and Intangible. The book Software Profit Streams by Tanner and Hohmann gives excellent insight into understanding value.
Just remember that story points or even items completed do not automatically equate to value. Items completed are output. The outcome is the goal and not always equal to your output.
Growth is its own topic and typically exists at the organization level, answering questions such as “Is our change effort working?”
What About Velocity?
Velocity is a useful measure for Sprint Planning — but it does not measure success. It offers a rough gauge of how much work to plan in the next Sprint based on past performance. Velocity can be horribly misused if shared up the management chain. There are better ways to predict when a team will be done or how effective it is.
Examples of the Four Metrics in Action
These charts are based on real data from teams I worked with and are a snapshot taken about ten months into an agile adoption. I tend to stick with a six-month rolling window because if you go much beyond that, things have changed so much as to be irrelevant to what the team is doing or working on now.
- Cycle Time

The spike represents the team moving to a new project and the ramp-up time as they got used to the work on the new project while going through a series of organizational changes.

- Escaped Defect Rate
This graph shows a fairly typical curve for a cross-functional team with the start of shared skills across individuals and the use of automated testing. With everyone in the team jointly responsible for the items in the Sprint, including product quality, and a greater focus on test automation, we see a dramatic drop in defects found in the product after release.
- Planned-to-Done Ratio

This team lost its ScrumMaster, which impacted its overall performance, as reflected in the first Sprint’s data. In the second sprint, an experienced ScrumMaster came in to help. The early dips represent the team getting used to a new set of norms, and the later dips were a result of changes in the program that reduced the clarity of the team’s backlog.

- Happiness Metric
The data shows how the support of the experienced ScrumMaster improved the team’s overall health. The graph also reflects that the churn in the product and organization impacted the team’s happiness later on.
Based on these graphs, I engaged with the team and listened to what had been going on in the last couple of sprints. The dip in the Planned-to-Done ratio and Happiness Metric were enough to tell me there might be something going on. The low cycle time and escaped defects led me to suspect the problems were external to the team.
The real challenges were coming from a chaotic product strategy that had the team bouncing around among priorities. The volatility in the backlog changes led to lower-quality stories. The team had sufficient experience to stop when they dug into a story they didn’t understand and shift to work they did. This lowered the Planned-to-Done ratio because not all planned work could be finished, while cycle time was low as they worked on things they understood well.
Agile Team Metrics Template
I’ve found success using these four interrelated metrics and encourage you to try them. Their interrelationship prevents gaming one measure without impacting others. They provide valuable data to the team for retrospective improvement, are meaningful to leadership, and help with forecasting.
If you want to try these metrics and create charts like those above, check out my Team Agile Metrics template here.